Issue Name: Space Allocation.
WBS: 2 Logged By: Joel Jacobson
Problem/Success: Space constraint to the contractor to work on replacing components.
Impact: Affected duration of the time to be worked on. Increased from 1 hour to an hour and a half.
Recommendations: In the long run, the Heater unit should be the same location as the laundry room for better space.
Follow-up:
Followed By:
Phase: Executing
Knowledge Area: Project Time Management